Category: Two Bedroom Dauin House
dauin home construction

FINISHING AND FENCING MARCH UPDATE

It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 angle bar, then  after placing…

FOOTINGS FOR COLUMNS AND WALLS

After the excavation, we have fabricated our steel reinforcing for the column and footings. Once set in place approximately 2″ above a 6″ layer of choker rock within the excavated holes, we pour cement. After the column footings are poured, we pour wall footings between the columns and start with the concrete hollow block. The…

demolition of existing house

SITE MOBILIZATION AND DEMOLITION

The first step has been to build a bunkhouse and bodega. Our men stay on iste during the week so we need a place for them to sleep, as well as a place to store our materials that is safe and dry. The next step is to get rid of the existing building on the…