Tag: building contractor
siquijor resort construction restaurant

PROGRESS JULY AND AUGUST

Installing the tiles in the cottages. Constructing the bamboo railings on the outside of the cottage terraces. Putting  the nipa roofing onto the restaurant wood framing compacting the floor for the restaurant, then rough in plumbing and electrical, tie rebar matting then pour cement for the slab. Finishing the restaurant with tiles, paint, firewall, etc

SPANISH STYLE VILLA CONSTRUCTION PROGRESS UPDATE 08 30

Layout and excavation for column footings Fabricating the rebar matting for footings and columns Pouring the footing then forming and pouring the columns with concrete Getting started on the cement hollow block walls Preparing the forms for the round columns on the terrace and putting in place  reinforcement for beams at the first floor Getting…

BALI STYLE COMMUNITY PROGRESS APRIL-JUNE

Since the last construction update, the big push has been on to get all the walls up. The exterior walls are all of 6″ CHB while most interior walls are 4″ Once the walls are up, we formed and poured the remaining column and started on fabricating the steel reinforcement for the future concrete roof…

DAUIN SEMI DETACHED HOME PROGRESS 06/30

A lot has happened on this construction project since we last posted an update around mid-March. Structural columns and beams made of reinforced concrete. Fabrication and installation of steel roof trusses. Electrical and plumbing rough-in. Parging of walls with cement rendering Framing of the ceilings. Installing fascia , eaves trough and metal roofing panels over…

VILLA CONSTRUCTION APRIL TO JUNE

CHB wall construction for the ground floor level Building columns with reinforcing rod, then forming and pouring concrete Stripping the basement roof forms and starting to excavate and prepare the master bedroom suite Building all the roof beams Putting up the Concrete Hollow Block Walls in the master bedroom Rendering the CHB walls Digging out,…

siquijor resort construction

APRIL TO JUNE PROGRESS

We now have 3 of the nipa roofs on and have started demolishing the existing water storage tank where the 4th cottage will go. We have applied Zemcoat finish to the wall and begun base coat primer paint. As well we have started the initial phases of the restaurant structure, pouring our footings and columns…

DAUIN SEMI DETACHED HOME CONSTRUCTION UPDATE 03/15

THIS HOUSE IS FOR SALE (ONLY 6.5 MIL PHP)- IF INTERESTED , PLEASE VISIT THIS LINK https://dumaguetedreamhomes.com/portfolio/casa-alexandria-dauin-community/#sd-duplex-1 After excavation, it is time to prepare and install the steel reinforing rod for the footing ,columns and tie beams. Being a 2 story structure on sandy soil , we use 16 mm rebar for everything to ensure…

VILLA CONSTRUCTION UPDATE MARCH 15TH

When we started excavation, we ran into a not totally unexpected issue. Being on a plateau in the hills there was the high likelihood that we would hit rock when digging and sure enough it was there. We adapted and decided that instead of doing a large scale excavation for the entire footprint of the…

sea wall construction

SEA WALL CONSTRUCTION AND FENCING

The cottage has basically been finished and turned over to the client, and now it is time to make the site secure and livable. We start with building a 2.2 meter high chb wall along the public access beach walkway. This involves constructing reinforced concrete columns, then filling in between with  concrete hollow block set…

CONTINUING SITE DEVELOPMENT

Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The next thing is…

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, painting,  terrace tiles and pebble finish.…

dauin home construction

FINISHING AND FENCING MARCH UPDATE

It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 angle bar, then  after placing…

GETTING STARTED

Time to start construction. We have laid out the building, taking extra care to ensure that the fire wall separation will site EXACTLY on the lot lines. We had our trusted surveyor relocate the mojon markers to make sure this was done right. We  then started excavation for the column and wall footings as well…

demolition of existing house

SITE MOBILIZATION AND DEMOLITION

The first step has been to build a bunkhouse and bodega. Our men stay on iste during the week so we need a place for them to sleep, as well as a place to store our materials that is safe and dry. The next step is to get rid of the existing building on the…

aluminum windows

ALMOST DONE

With only a little over 1 week until the clients are here in the Philippines, are hard work seems to be paying off. For the most part all that is left are some of the details of the finishing. Doors have been installed however we have found some issues. When we unpackaged them, there are…

steel post and wire railing

PAINTING AND RAILING

Still pushed to the deadline, our men are responding well with dedication  and commitment. We are putting on the backsplash tiles in the downstairs kitchen, progressing well with the cabinets in the mini-kitchen upstairs, and have installed a steel frame and wire railing on the outside second floor terrace.