PROGRESS JULY AND AUGUST

Installing the tiles in the cottages. Constructing the bamboo railings on the outside of the cottage terraces. Putting  the nipa roofing onto the restaurant wood framing compacting the floor for the restaurant, then rough in plumbing and electrical, tie rebar matting then pour cement for the slab. Finishing the restaurant with tiles, paint, firewall, etc

DAUIN SEMI DETACHED HOME PROGRESS 06/30

A lot has happened on this construction project since we last posted an update around mid-March. Structural columns and beams made of reinforced concrete. Fabrication and installation of steel roof trusses. Electrical and plumbing rough-in. Parging of walls with cement rendering Framing of the ceilings. Installing fascia , eaves trough and metal roofing panels over…

DAUIN SEMI DETACHED HOME CONSTRUCTION UPDATE 03/15

THIS HOUSE IS FOR SALE (ONLY 6.5 MIL PHP)- IF INTERESTED , PLEASE VISIT THIS LINK https://dumaguetedreamhomes.com/portfolio/casa-alexandria-dauin-community/#sd-duplex-1 After excavation, it is time to prepare and install the steel reinforing rod for the footing ,columns and tie beams. Being a 2 story structure on sandy soil , we use 16 mm rebar for everything to ensure…

dauin home construction

FINISHING AND FENCING MARCH UPDATE

It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 angle bar, then  after placing…

construction of wall

FENCING

Now that the house is complete and the clients occupying it, they have decided that the next phases of development will be site upgrades including wall and fencing. The existing fencing on the North boundary beside the road, consisted of precast cement posts, a knee high cement hollow block wall, topped with chain link fencing.…

floor, ceiling and insulation

FLOOR , CEILING AND WALLS

Now that our structural work is done on the floor, we have been able to work on the plywood sub-floor. with the plywood on we now have a walking and working surface to be able to carry on with other upstairs work. We have installed steel stud walls and a steel furring channel system for…

suspended ceiling with insulation

CEILING AND INSULATION

With the building now closed in and water tight, we have started on the ceiling. It will be a drop type  ceiling following the slope of the roof in cathedral style in the living room and bedroom, and horizontal in the kitchen, washroom and laundry. It is being constructed with furring channels tied to the…

taping and sanding of drywall ceiling

TAPING AND SANDING OF THE CEILING

Before finishing the drywall application of the ceiling, we do one last check to ensure all the plumbing and electrical to be located within the ceiling is 100% complete. Once all the base coat of the walls is complete and the grid and boarding of the ceiling finished, our next step is the taping and…

SKIM COATING OF WALLS

With all the electrical and plumbing roughing done, we have turned our attention to finishing all the walls. What we have found to be best for this is a product called Zemcoat which is applied over the rough cement parging finishing of the concrete hollow block walls. With that process nearly complete, our next plans…

FINISHING AND TURNOVER

With the client pushing for turnover of the completed project as soon as possible so that they can commence operations, the push is on to finalize all the finishing details. Doors need to be hung, painting touch ups completed and both the electrical and air conditioning systems requiring energization and testing, our men are working…

A/C, FLOORING AND CEILING

With the electrical roughing all complete, we then started on Air conditioning, ceiling and flooring. The client provided 3 five ton floor models which were used for the main call center floor and for all the offices we used new split type inverter units. All compressors were mounted on the exterior catwalk adjacent to the…