Balinese Style Home Progress July to December

With the passing of 6 months, there has been plenty of work done, and with the start of 2019, the home construction is almost complete. There will be small odds and ends, but this is not stopping the happy client from making last minute arrangements to move in. Now that the roofing is on and…

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, painting,  terrace tiles and pebble finish.…

sanding a wood plank floor

SANDING THE WOOD PLANK FLOOR AND MORE

Well we received our missing wood and it is not a total disaster. The grain and color of the new wood is not much different and we have decided to use it. Now installed, we have planed and sanded the entire floor to a nice even and smooth finish and it is ready to accept…

painting the exterior of the home

PAINTING

With the majority of the basic work finished, we are touching up interior walls to prepare for painting. We are also doing the painting for the exterior.

tiling

TILING

With the painting of one unit complete, the painter has moved over to the next and allowed us to get started on the tiling. Tiles are set with a mixture of cement and tile grip and carefully leveled.  We will continue on with this progression of work so that the different trades men are not…

painting of walls and ceilings

PAINTING OF WALLS AND CEILINGS

With most of the sanding and painting complete, we now move on to the finish painting. This will be done in a phased approach since there are 4 units in this apartment block. We do want to make sure all painting is complete in a unit before we start the tiling, so after one unit…

suspended ceiling and painting

CEILING AND PAINT BASE COAT

With the skim coat finished on the wall, we now start the ceiling grid layout and base coat painting of the walls. The ceiling is suspended with a grid of furring channels and for the top floor we cut and place semi rigid rockwool insulation as both a sound barrier to rain on the metal…

FINISHING AND TURNOVER

With the client pushing for turnover of the completed project as soon as possible so that they can commence operations, the push is on to finalize all the finishing details. Doors need to be hung, painting touch ups completed and both the electrical and air conditioning systems requiring energization and testing, our men are working…

house construction finishing

SAN MIGUEL HOUSE FINISHING

Our Clients have graciously been a little flexible on the turn-over date of their new home, due to the typical slowdown over the Christmas Holidays. Currently we are at the finishing stages of this construction and are completing tiling, cabinets and granite counter tops, painting, plumbing and electrical fixtures. Our major push in the closing…

APPROACHING TURNOVER DATE

We are now getting close to the turnover date to the client and things are going fast and furious in attempt to meet our deadline of September 30th. We are concurrently doing the tiling, painting, kitchen cabinets, electrical fixtures and much much more. With so many tradesmen working in the same area at one time,…

JULY PROGRESS

July Progress With the date fast approaching when the clients will be returning to the Philippines for a vacation, we are under a very tight deadline to complete the washroom renovation phase to the stage where it can be occupied and used. Working two shifts, we are doing the finishing touches including instaltion of electrical…