Tag: tiling
siquijor resort construction restaurant

PROGRESS JULY AND AUGUST

Installing the tiles in the cottages. Constructing the bamboo railings on the outside of the cottage terraces. Putting  the nipa roofing onto the restaurant wood framing compacting the floor for the restaurant, then rough in plumbing and electrical, tie rebar matting then pour cement for the slab. Finishing the restaurant with tiles, paint, firewall, etc

house construction finishing

SAN MIGUEL HOUSE FINISHING

Our Clients have graciously been a little flexible on the turn-over date of their new home, due to the typical slowdown over the Christmas Holidays. Currently we are at the finishing stages of this construction and are completing tiling, cabinets and granite counter tops, painting, plumbing and electrical fixtures. Our major push in the closing…

APPROACHING TURNOVER DATE

We are now getting close to the turnover date to the client and things are going fast and furious in attempt to meet our deadline of September 30th. We are concurrently doing the tiling, painting, kitchen cabinets, electrical fixtures and much much more. With so many tradesmen working in the same area at one time,…