Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/negrosconstruction.com/public_html/wp-includes/functions.php on line 6121
September 2018 - Negros Construction

Monthly Archives: September 2018

PROGRESS JULY AND AUGUST

PROGRESS JULY AND AUGUST

PROGRESS JULY AND AUGUST Installing the tiles in the cottages. Constructing the bamboo railings on the outside of the cottage terraces. Putting the nipa roofing onto the restaurant wood framing compacting the floor for the restaurant, then rough in plumbing and electrical, tie rebar matting then pour cement for the slab. Finishing the restaurant with […]