Classic Blog

March 18 2018 0comment

DAUIN SEMI DETACHED HOME CONSTRUCTION UPDATE 03/15

THIS HOUSE IS FOR SALE (ONLY 6.5 MIL PHP)- IF INTERESTED , PLEASE VISIT THIS LINK https://dumaguetedreamhomes.com/portfolio/casa-alexandria-dauin-community/#sd-duplex-1 After excavation, it is time to prepare and install the steel reinforing rod for the footing ,columns and tie beams. Being a 2 story structure on sandy soil , we use 16 mm rebar for everything to ensure […]

March 17 2018 0comment

HOME CONSTRUCTION UPDATE MAR 15

The first thing we do, like all jobs we start is to layout or “plot” the location where the builing is going to sit on the property. We do this with our surveyor Josh Cabio of I-Sukod to ensure no mistakes are made. We then start excavation whehr the column and wall footings will go. […]

March 16 2018 0comment

VILLA CONSTRUCTION UPDATE MARCH 15TH

When we started excavation, we ran into a not totally unexpected issue. Being on a plateau in the hills there was the high likelihood that we would hit rock when digging and sure enough it was there. We adapted and decided that instead of doing a large scale excavation for the entire footprint of the […]

March 12 2018 0comment
sea wall construction

SEA WALL CONSTRUCTION AND FENCING

The cottage has basically been finished and turned over to the client, and now it is time to make the site secure and livable. We start with building a 2.2 meter high chb wall along the public access beach walkway. This involves constructing reinforced concrete columns, then filling in between with  concrete hollow block set […]

March 11 2018 0comment

CONTINUING SITE DEVELOPMENT

Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The next thing is […]

March 11 2018 0comment

CONSTRUCTION ONGOING FEBRUARY 2018 SIQUIJOR RESORT

We started by laying out the different buildings with the help of our surveyor Josh Cabio. When we knew where everything was going we began demolishing the existing structures that were going to be in the way. We left 2 structures that were built on top of water reservoirs so that we would still be […]

March 11 2018 0comment

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, painting,  terrace tiles and pebble finish. […]

March 11 2018 0comment
dauin home construction

FINISHING AND FENCING MARCH UPDATE

It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 angle bar, then  after placing […]

January 31 2018 0comment
construction of wall

FENCING

Now that the house is complete and the clients occupying it, they have decided that the next phases of development will be site upgrades including wall and fencing. The existing fencing on the North boundary beside the road, consisted of precast cement posts, a knee high cement hollow block wall, topped with chain link fencing. […]

January 23 2018 0comment

GETTING STARTED

Time to start construction. We have laid out the building, taking extra care to ensure that the fire wall separation will site EXACTLY on the lot lines. We had our trusted surveyor relocate the mojon markers to make sure this was done right. We  then started excavation for the column and wall footings as well […]

October 31 2017 0comment
electrical rough in

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING

With the chb walls up, the next steps are to inset all the conduits for the electrical. That done, we have proceeding on to the rendering of the walls. This is done with a mixture of cement applied to the hollow block in a uniform parging coat. While some men are working on that, other […]

October 31 2017 0comment
chb walls

CHB WALLS AND SEPTIC TANK

For the walls, we have used a special mixture cement hollow block, with 10 mm steel reinforcing rod tied in both horizontally and vertically. Over all doors and windows we have formed a reinforced concrete lintel.

October 31 2017 0comment

FOOTINGS FOR COLUMNS AND WALLS

After the excavation, we have fabricated our steel reinforcing for the column and footings. Once set in place approximately 2″ above a 6″ layer of choker rock within the excavated holes, we pour cement. After the column footings are poured, we pour wall footings between the columns and start with the concrete hollow block. The […]

October 31 2017 2Comments
demolition of existing house

SITE MOBILIZATION AND DEMOLITION

The first step has been to build a bunkhouse and bodega. Our men stay on iste during the week so we need a place for them to sleep, as well as a place to store our materials that is safe and dry. The next step is to get rid of the existing building on the […]

October 26 2017 0comment
laminate wood flooring

LAMINATE WOOD FLOORING AND CABINET DOORS

Well, almost there. We have finished the laminate wood flooring on the second story level and have put on the cabinet doors in the downstairs kitchen. Only thing left is baseboards then a good clean before the clients arrive in 2-3 days, and then it will be ready for their use and enjoyment.

October 26 2017 0comment
aluminum windows

ALMOST DONE

With only a little over 1 week until the clients are here in the Philippines, are hard work seems to be paying off. For the most part all that is left are some of the details of the finishing. Doors have been installed however we have found some issues. When we unpackaged them, there are […]