With the building now roofed and water tight, we review one final time all the electrical pipes and electrical conduits that are roughed in. We have already compacted the granular fill for the floor and now lay our steel matting which will reinforce the concrete floor slab. Once we are satisfied that everything is in place properly we schedule the floor slab pour. For the pour, we want to ensure that it is complete all in one day, so we pull additional crew and mixing equipment from another job site. The floor slab is poured successfully in one very long day.
We have also been busy constructing the 3 chamber septic system, with all walls finished and plumbing roughed in.