SIBULAN BEACH HOUSE – MAIN HOUSE START
With the clients succesfully in their new Nipa House by the end of December, it was time to begin the main structures. The next one is to be the 3 bedroom structure, which again will be built from native materials , however wull be build on reinforced cement footings, with concrete columns. the floor will also be a cement slab. To begin, we have excavated and pired column and wall footings, and are now working on the hollow block knee walls which will border the floor slab.