WALL FINISHING, SEPTIC TANK, ROOF FRAMING

With the Structure complete and the concrete hollow block walls up, we have been working on the cement parging of all interior and interior walls , digging and construction the septic tank and framing the roof structure with site fabricated trusses. All is progressing according to plan, and the scheduling appears to be on track.