Notice: Function _load_textdomain_just_in_time was called incorrectly. Translation loading for the acf domain was triggered too early. This is usually an indicator for some code in the plugin or theme running too early. Translations should be loaded at the init action or later. Please see Debugging in WordPress for more information. (This message was added in version 6.7.0.) in /home/negrosconstruction.com/public_html/wp-includes/functions.php on line 6121
August 2018 - Negros Construction

Monthly Archives: August 2018

SPANISH STYLE VILLA CONSTRUCTION PROGRESS UPDATE 08 30

SPANISH STYLE VILLA CONSTRUCTION PROGRESS UPDATE 08 30

SPANISH STYLE VILLA CONSTRUCTION PROGRESS UPDATE 08 30 Layout and excavation for column footings Fabricating the rebar matting for footings and columns Pouring the footing then forming and pouring the columns with concrete Getting started on the cement hollow block walls Preparing the forms for the round columns on the terrace and putting in place […]

Siquijor Beach Cottage Progress Report 08 23

Siquijor Beach Cottage Progress Report 08 23

Siquijor Beach Cottage Progress Report 08 23 Lay out and preparation of column footings Getting started on the rebar for the beams and proceeding with the cement hollow block walls.  

SIQUIJOR BEACH HOUSE CONSTRUCTION PROGRESS TO 08/20

SIQUIJOR BEACH HOUSE CONSTRUCTION PROGRESS TO 08/20

SIQUIJOR BEACH HOUSE CONSTRUCTION PROGRESS TO 08/20 Laying out the location of the home with the help of our surveyor Getting started by pouring the column and wall footing , then the first few rows of concrete hollow block   Continuing up with the chb walls Preparing the rebar and constructing the forms for the […]