COLUMNS Footing complete, our next job is to tie all our column rebar frames into the footings as well as connecting all column rebar to the tie beam rebar. The these pours will take place in two stages. The first will be hich enough so that the bottom portion of the columns will be done […]
Monthly Archives: September 2016
The columns are now poured and the forms stripped so it is time to start constructing the beams for the second story. Again we start by constructing the rebar reinforcing frames, which we tie into the exposed rebar at the top of the columns. Once all this is securely in place, we build forms that […]
All the beams are now in place and poured. We now turn our boys to the task of preparing for the second story floor slab. This involves putting together all the wood forms and bracing them properly from below to temporarily hold the weight of the slab until it sets properly. We also must lay […]
May Progress With all the structural remedial work completed , we have moved on to the basic layout of concrete hollow block walls, electrical and plumbing roughing.
June Progress After completing all the necesaary roughing for plumbing and electrical, finalizing of all interior partion , concrete hollow block walls, and pouring the new reinforced concrete floor slab, we were ready to start the basic finishing. This included tiling, preparation of wall surface, cabinets and cupboards.
July Progress With the date fast approaching when the clients will be returning to the Philippines for a vacation, we are under a very tight deadline to complete the washroom renovation phase to the stage where it can be occupied and used. Working two shifts, we are doing the finishing touches including instaltion of electrical […]