Tag: Builder

BALI STYLE COMMUNITY PROGRESS APRIL-JUNE

Since the last construction update, the big push has been on to get all the walls up. The exterior walls are all of 6″ CHB while most interior walls are 4″ Once the walls are up, we formed and poured the remaining column and started on fabricating the steel reinforcement for the future concrete roof…

sea wall construction

SEA WALL CONSTRUCTION AND FENCING

The cottage has basically been finished and turned over to the client, and now it is time to make the site secure and livable. We start with building a 2.2 meter high chb wall along the public access beach walkway. This involves constructing reinforced concrete columns, then filling in between with  concrete hollow block set…

CONTINUING SITE DEVELOPMENT

Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The next thing is…

CONSTRUCTION ONGOING FEBRUARY 2018 SIQUIJOR RESORT

We started by laying out the different buildings with the help of our surveyor Josh Cabio. When we knew where everything was going we began demolishing the existing structures that were going to be in the way. We left 2 structures that were built on top of water reservoirs so that we would still be…

taping and sanding of drywall ceiling

TAPING AND SANDING OF THE CEILING

Before finishing the drywall application of the ceiling, we do one last check to ensure all the plumbing and electrical to be located within the ceiling is 100% complete. Once all the base coat of the walls is complete and the grid and boarding of the ceiling finished, our next step is the taping and…

modern - balinese style community

SITE DEVELOPMENT

With this project, there will be many components that all have to fit in together/ Careful planning has to be done so that all the site infrastructure is completed properly in the right locations or the entire community lay out will be affected. The first thing we have done is get in a geodetic engineer…

COLUMNS AND WALLS

We have poured the first lift of the columns and also got well into the beginning of the walls. The walls are concrete hollow block with 10mm reinforcing bar, set on reinforced concrete wall footings. The walls are being tied into the adjacent columns to with rebar to ensure there is minimal movement between walls…

GETTING READY FOR FRAMING

On this project, we have been working on the interior walls because though it is an open type structure, there is a washroom storeroom and a semi closed kitchen area. These walls are being built with concrete hollow block sitting on reinforced concrete wall footings. We have also received all our lumber for the roof…

FLOOR SLAB AND ROOF FRAMING

With all the walls complete, columns pored and roughing for electrical and plumbing laid out, our construction crew moves on to their next tasks. While the walls were being laid, we had our steelworkers construct the trusses so that immediately after we could start the roof framing, including rafters and c-channels. Once the roof framing…

WALL RENDERING

After the second floor slab was completed, we turned our attention to the walls. All interior and exterior walls were constructed using 4″ or 6″ concrete hollow block , with steel reinforcing rod and full fill of cement. After the walls are constructed, we apply a cement parging finish which is trowel graded to a…

TURNOVER TO CLIENT

Today is turnover day, and things are almost complete. We are rushing last minute work to make the house livable, then will allow the client to move in and realx for a few days before completing the remaining work and fixing any deficiencies.