Tag: dumaguete construction
siquijor resort construction restaurant

PROGRESS JULY AND AUGUST

Installing the tiles in the cottages. Constructing the bamboo railings on the outside of the cottage terraces. Putting  the nipa roofing onto the restaurant wood framing compacting the floor for the restaurant, then rough in plumbing and electrical, tie rebar matting then pour cement for the slab. Finishing the restaurant with tiles, paint, firewall, etc

SPANISH STYLE VILLA CONSTRUCTION PROGRESS UPDATE 08 30

Layout and excavation for column footings Fabricating the rebar matting for footings and columns Pouring the footing then forming and pouring the columns with concrete Getting started on the cement hollow block walls Preparing the forms for the round columns on the terrace and putting in place  reinforcement for beams at the first floor Getting…

BALI STYLE COMMUNITY PROGRESS APRIL-JUNE

Since the last construction update, the big push has been on to get all the walls up. The exterior walls are all of 6″ CHB while most interior walls are 4″ Once the walls are up, we formed and poured the remaining column and started on fabricating the steel reinforcement for the future concrete roof…

DAUIN SEMI DETACHED HOME CONSTRUCTION UPDATE 03/15

THIS HOUSE IS FOR SALE (ONLY 6.5 MIL PHP)- IF INTERESTED , PLEASE VISIT THIS LINK https://dumaguetedreamhomes.com/portfolio/casa-alexandria-dauin-community/#sd-duplex-1 After excavation, it is time to prepare and install the steel reinforing rod for the footing ,columns and tie beams. Being a 2 story structure on sandy soil , we use 16 mm rebar for everything to ensure…

HOME CONSTRUCTION UPDATE MAR 15

The first thing we do, like all jobs we start is to layout or “plot” the location where the builing is going to sit on the property. We do this with our surveyor Josh Cabio of I-Sukod to ensure no mistakes are made. We then start excavation whehr the column and wall footings will go.…

VILLA CONSTRUCTION UPDATE MARCH 15TH

When we started excavation, we ran into a not totally unexpected issue. Being on a plateau in the hills there was the high likelihood that we would hit rock when digging and sure enough it was there. We adapted and decided that instead of doing a large scale excavation for the entire footprint of the…

sea wall construction

SEA WALL CONSTRUCTION AND FENCING

The cottage has basically been finished and turned over to the client, and now it is time to make the site secure and livable. We start with building a 2.2 meter high chb wall along the public access beach walkway. This involves constructing reinforced concrete columns, then filling in between with  concrete hollow block set…

CONTINUING SITE DEVELOPMENT

Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The next thing is…

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, painting,  terrace tiles and pebble finish.…

dauin home construction

FINISHING AND FENCING MARCH UPDATE

It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 angle bar, then  after placing…

GETTING STARTED

Time to start construction. We have laid out the building, taking extra care to ensure that the fire wall separation will site EXACTLY on the lot lines. We had our trusted surveyor relocate the mojon markers to make sure this was done right. We  then started excavation for the column and wall footings as well…

kitchen renovation

GOING FLAT TO THE WALL

The impending turnover deadline is fast approaching so we are working all out with 2 crews and over 40 workmen on site each day. The kitchen renovation is nearing completion with the installation of the granite counter tops and the finishing of the ceiling.  Downstairs we have also re-used some of the existing tiles that…

partition walls tiling washroom , well and stair structure

INTERIOR PARTITION WALLS AND KITCHEN RENOVATION

While some men are finishing the ceiling and wall insulation and plywood flooring, other men have started framing the interior partition walls upstairs. At the same time, we have dug into the renovation of the kitchen downstairs, which was a client add on. We have gutted the kitchen and are building a decorative suspended ceiling…

floor, ceiling and insulation

FLOOR , CEILING AND WALLS

Now that our structural work is done on the floor, we have been able to work on the plywood sub-floor. with the plywood on we now have a walking and working surface to be able to carry on with other upstairs work. We have installed steel stud walls and a steel furring channel system for…

painting the exterior of the home

PAINTING

With the majority of the basic work finished, we are touching up interior walls to prepare for painting. We are also doing the painting for the exterior.

kitchen cabinets

CABINETS AND TILING

Next we are moving on to the tiling, after which we can start installing kitchen cabinets and bedroom closet. These cabinets are made from Sant Clara finish plywood and are being prfabricated outside of the house to be secured in place after the tiling.