Tag: home construction

Balinese Style Home Progress July to December

With the passing of 6 months, there has been plenty of work done, and with the start of 2019, the home construction is almost complete. There will be small odds and ends, but this is not stopping the happy client from making last minute arrangements to move in. Now that the roofing is on and…

BALI STYLE COMMUNITY PROGRESS APRIL-JUNE

Since the last construction update, the big push has been on to get all the walls up. The exterior walls are all of 6″ CHB while most interior walls are 4″ Once the walls are up, we formed and poured the remaining column and started on fabricating the steel reinforcement for the future concrete roof…

DAUIN SEMI DETACHED HOME PROGRESS 06/30

A lot has happened on this construction project since we last posted an update around mid-March. Structural columns and beams made of reinforced concrete. Fabrication and installation of steel roof trusses. Electrical and plumbing rough-in. Parging of walls with cement rendering Framing of the ceilings. Installing fascia , eaves trough and metal roofing panels over…

DAUIN SEMI DETACHED HOME CONSTRUCTION UPDATE 03/15

THIS HOUSE IS FOR SALE (ONLY 6.5 MIL PHP)- IF INTERESTED , PLEASE VISIT THIS LINK https://dumaguetedreamhomes.com/portfolio/casa-alexandria-dauin-community/#sd-duplex-1 After excavation, it is time to prepare and install the steel reinforing rod for the footing ,columns and tie beams. Being a 2 story structure on sandy soil , we use 16 mm rebar for everything to ensure…

HOME CONSTRUCTION UPDATE MAR 15

The first thing we do, like all jobs we start is to layout or “plot” the location where the builing is going to sit on the property. We do this with our surveyor Josh Cabio of I-Sukod to ensure no mistakes are made. We then start excavation whehr the column and wall footings will go.…

CONTINUING SITE DEVELOPMENT

Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The next thing is…

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, painting,  terrace tiles and pebble finish.…

dauin home construction

FINISHING AND FENCING MARCH UPDATE

It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 angle bar, then  after placing…

construction of wall

FENCING

Now that the house is complete and the clients occupying it, they have decided that the next phases of development will be site upgrades including wall and fencing. The existing fencing on the North boundary beside the road, consisted of precast cement posts, a knee high cement hollow block wall, topped with chain link fencing.…

FOOTINGS FOR COLUMNS AND WALLS

After the excavation, we have fabricated our steel reinforcing for the column and footings. Once set in place approximately 2″ above a 6″ layer of choker rock within the excavated holes, we pour cement. After the column footings are poured, we pour wall footings between the columns and start with the concrete hollow block. The…

demolition of existing house

SITE MOBILIZATION AND DEMOLITION

The first step has been to build a bunkhouse and bodega. Our men stay on iste during the week so we need a place for them to sleep, as well as a place to store our materials that is safe and dry. The next step is to get rid of the existing building on the…

laminate wood flooring

LAMINATE WOOD FLOORING AND CABINET DOORS

Well, almost there. We have finished the laminate wood flooring on the second story level and have put on the cabinet doors in the downstairs kitchen. Only thing left is baseboards then a good clean before the clients arrive in 2-3 days, and then it will be ready for their use and enjoyment.

partition walls tiling washroom , well and stair structure

INTERIOR PARTITION WALLS AND KITCHEN RENOVATION

While some men are finishing the ceiling and wall insulation and plywood flooring, other men have started framing the interior partition walls upstairs. At the same time, we have dug into the renovation of the kitchen downstairs, which was a client add on. We have gutted the kitchen and are building a decorative suspended ceiling…

sanding a wood plank floor

SANDING THE WOOD PLANK FLOOR AND MORE

Well we received our missing wood and it is not a total disaster. The grain and color of the new wood is not much different and we have decided to use it. Now installed, we have planed and sanded the entire floor to a nice even and smooth finish and it is ready to accept…

painting the exterior of the home

PAINTING

With the majority of the basic work finished, we are touching up interior walls to prepare for painting. We are also doing the painting for the exterior.