PROGRESS JULY AND AUGUST

Installing the tiles in the cottages. Constructing the bamboo railings on the outside of the cottage terraces. Putting  the nipa roofing onto the restaurant wood framing compacting the floor for the restaurant, then rough in plumbing and electrical, tie rebar matting then pour cement for the slab. Finishing the restaurant with tiles, paint, firewall, etc

CONTINUING SITE DEVELOPMENT

Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The next thing is…

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, painting,  terrace tiles and pebble finish.…

STRUCTURE NEARING COMPLETION

This native hybrid house construction project is moving along very nicely. With only about 6 weeks of time gone by, the structure itself is nearing completion. The concrete hollow block walls are all up on the ground floor and the wood framing of the second floor has been completed. We have put in the roughing…

BEAMS

The columns are now poured and the forms stripped so it is time to start constructing the beams for the second story. Again we start by constructing the rebar reinforcing frames, which we tie into the exposed rebar at the top of the columns. Once all this is securely in place, we build forms that…

ROOFING AND CLOSE IN

With the walls, columns and beams all structurally complete, we now fabricate steel joists to form the structural element of the roofing system. This is a two slope layout with the highest elevation near the middle of the building, sloping to the outside walls where it goes through through the opening between the exterior double…