Tag: house building

Balinese Style Home Progress July to December

With the passing of 6 months, there has been plenty of work done, and with the start of 2019, the home construction is almost complete. There will be small odds and ends, but this is not stopping the happy client from making last minute arrangements to move in. Now that the roofing is on and…

STARTING THE FINISHING WORK

Over the past week or two we have been working on several different things. We have installed all the Amakan soffit on the underside of the eaves and fitted on fascia boards. We have also started the framing of the terrace which will be native style with Lauan wood joists and purlins with Nipa roofing.…

call center tenant fit up

CALL CENTER PROGRESS JAN 15

Though we had been awarded this contract in late December, with the holidays approaching, and the main construction site closed down, we decided to hold off our start until the New Year. Upon start-up in January, the first thing that need to be addressed was the raw concrete floor. The leased area was turned over…