Gordon Mckissock, Author at Negros Construction - Page 5 of 15

Author Archives: Gordon Mckissock

CONTINUING SITE DEVELOPMENT

CONTINUING SITE DEVELOPMENT

CONTINUING SITE DEVELOPMENT Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The […]

FINISHING AND FENCING MARCH UPDATE

FINISHING AND FENCING MARCH UPDATE

FINISHING AND FENCING MARCH UPDATE It’s been a long time since the last post on this construction project, so a lot to go over. Back in November we had just finished the parging/rendering on the hollow block walls and then began the roof framing. This was done by site fabrication of steel trusses using 2×2 […]

FENCING

FENCING

FENCING Now that the house is complete and the clients occupying it, they have decided that the next phases of development will be site upgrades including wall and fencing. The existing fencing on the North boundary beside the road, consisted of precast cement posts, a knee high cement hollow block wall, topped with chain link […]

GETTING STARTED

GETTING STARTED

GETTING STARTED Time to start construction. We have laid out the building, taking extra care to ensure that theGETTING STARTED fire wall separation will site EXACTLY on the lot lines. We had our trusted surveyor relocate the mojon markers to make sure this was done right. We then started excavation for the column and wall […]

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING With the chb walls up, the next steps are to inset all the conduits for the electrical. That done, we have proceeding on to the rendering of the walls. This is done with a mixture of cement applied to the hollow block in a uniform parging coat. While some […]

FOOTINGS FOR COLUMNS AND WALLS

FOOTINGS FOR COLUMNS AND WALLS

FOOTINGS FOR COLUMNS AND WALLS After the excavation, we have fabricated our steel reinforcing for the column and footings. Once set in place approximately 2″ above a 6″ layer of choker rock within the excavated holes, we pour cement. After the column footings are poured, we pour wall footings between the columns and start with […]

SITE MOBILIZATION AND DEMOLITION

SITE MOBILIZATION AND DEMOLITION

SITE MOBILIZATION AND DEMOLITION The first step has been to build a bunkhouse and bodega. Our men stay on iste during the week so we need a place for them to sleep, as well as a place to store our materials that is safe and dry. The next step is to get rid of the […]

CHB WALLS AND SEPTIC TANK

CHB WALLS AND SEPTIC TANK

CHB WALLS AND SEPTIC TANK For the walls, we have used a special mixture cement hollow block, with 10 mm steel reinforcing rod tied in both horizontally and vertically. Over all doors and windows we have formed a reinforced concrete lintel.