With the building now roofed and water tight, we review one final time all the electrical pipes and electrical conduits that are roughed in. We have already compacted the granular fill for the floor and now lay our steel matting which will reinforce the concrete floor slab. Once we are satisfied that everything is in […]
Author Archives: admin
INTERIOR AND EXTERIOR FINISHING Now with the concrete floor slab complete, we turn our attention to both interior and exterior finish. On the interior, the walls are sanded once again and treated with a smoothing compound. A base coat of primer is applied to the walls after the compound is thoroughly dry. The same process […]
All the beams are now in place and poured. We now turn our boys to the task of preparing for the second story floor slab. This involves putting together all the wood forms and bracing them properly from below to temporarily hold the weight of the slab until it sets properly. We also must lay […]
The columns are now poured and the forms stripped so it is time to start constructing the beams for the second story. Again we start by constructing the rebar reinforcing frames, which we tie into the exposed rebar at the top of the columns. Once all this is securely in place, we build forms that […]
COLUMNS Footing complete, our next job is to tie all our column rebar frames into the footings as well as connecting all column rebar to the tie beam rebar. The these pours will take place in two stages. The first will be hich enough so that the bottom portion of the columns will be done […]
PREPARING THE REBAR Excavation complete, we start putting together all the rebar frames which will serve as reinforcement within the poured concrete footings and tie beams. Once ready we again take precise measuremnts and set the frames in place. We check everything is located properly one last time then pour the concrete for all our […]
LAYOUT AND EXCAVATION With the temporary facilities set up, the layout of the building footprint begins. Once precise measurements are taken and stakes laid out, the men excavate by hand. The soil is found to be extremely soft and porous which is a concern. In order remove the risk of future settlement and cracking of […]
July Progress With the date fast approaching when the clients will be returning to the Philippines for a vacation, we are under a very tight deadline to complete the washroom renovation phase to the stage where it can be occupied and used. Working two shifts, we are doing the finishing touches including instaltion of electrical […]
June Progress After completing all the necesaary roughing for plumbing and electrical, finalizing of all interior partion , concrete hollow block walls, and pouring the new reinforced concrete floor slab, we were ready to start the basic finishing. This included tiling, preparation of wall surface, cabinets and cupboards.
May Progress With all the structural remedial work completed , we have moved on to the basic layout of concrete hollow block walls, electrical and plumbing roughing.