CONTINUING SITE DEVELOPMENT

CONTINUING SITE DEVELOPMENT

CONTINUING SITE DEVELOPMENT Site Development for this project involves many different components. The first thing we have done is build a large bunk house and storage facility. For this project, we will be here for a longer period and have many more workers than normal so we have not skimped on size and space. The […]

CONSTRUCTION ONGOING FEBRUARY 2018 SIQUIJOR RESORT

CONSTRUCTION ONGOING FEBRUARY 2018 SIQUIJOR RESORT

CONSTRUCTION ONGOING FEBRUARY 2018 SIQUIJOR RESORT We started by laying out the different buildings with the help of our surveyor Josh Cabio. When we knew where everything was going we began demolishing the existing structures that were going to be in the way. We left 2 structures that were built on top of water reservoirs […]

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE

DAUIN BEACH SIDE COTTAGE JANUARY UPDATE Since our last update in October, a lot has happened. Interior finishing has been ongoing including kitchen cabinets, granite counter tops, tile backsplash and decorative wood beams on the suspended ceiling, all in conjunction with sanding and painting. On the exterior we have been working on the stone cladding, […]

GETTING STARTED

GETTING STARTED

GETTING STARTED Time to start construction. We have laid out the building, taking extra care to ensure that theGETTING STARTED fire wall separation will site EXACTLY on the lot lines. We had our trusted surveyor relocate the mojon markers to make sure this was done right. We then started excavation for the column and wall […]

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING

ROOF BEAMS, ELECTRICAL ROUGHING AND RENDERING With the chb walls up, the next steps are to inset all the conduits for the electrical. That done, we have proceeding on to the rendering of the walls. This is done with a mixture of cement applied to the hollow block in a uniform parging coat. While some […]

FOOTINGS FOR COLUMNS AND WALLS

FOOTINGS FOR COLUMNS AND WALLS

FOOTINGS FOR COLUMNS AND WALLS After the excavation, we have fabricated our steel reinforcing for the column and footings. Once set in place approximately 2″ above a 6″ layer of choker rock within the excavated holes, we pour cement. After the column footings are poured, we pour wall footings between the columns and start with […]

SITE MOBILIZATION AND DEMOLITION

SITE MOBILIZATION AND DEMOLITION

SITE MOBILIZATION AND DEMOLITION The first step has been to build a bunkhouse and bodega. Our men stay on iste during the week so we need a place for them to sleep, as well as a place to store our materials that is safe and dry. The next step is to get rid of the […]